November 27, 2024

Seattleā€™s Alaskan Way Viaduct Replacement tunnel, shown during construction, opened to traffic two years late in 2019.
PHOTO COURTESY WSDOT
A panel of Washington state judges ruled Sept. 15 that insurers don’t owe payment, under a builder’s all-risk policy, to the contracting team and the state transportation department for a two-mile-long Seattle tunnel project, completed in 2019. The claim, by Seattle Tunnel Partners and the owner of the tunnel boring machine, Hitachi, was the most recent failed attempt to recover some of the money lost during a two-year delay in the $2.15-billion SR 99 Alaskan Way Viaduct Replacement Tunnel project, along Seattle’s waterfront.
The projectā€™s tunnel boring machine (TBM), nicknamed Bertha, shut down operations from December 2013-15 after the cutter head struck a steel pipe, sustaining damage. It didn’t get rolling again until 2016.
Seattle Tunnel Partners (TSP), led by Tutor Perini Co., failed in a lawsuit that sought additional payment from the Washington State Dept. of Transportation. TSP claimed the pipe was a differing site condition.
TSP also filed for coverage under its buildersā€™ risk insurance policy against a collection of insurers and insurance syndicates, including Zurich and Allianz, and the state transportationĀ department joined parts of the suit.
Specifically, the lawsuit filed in state court in Seattle is an appeal of a trial court decision that denied most of the claim in motion for summary judgement by the insurersā€”a motion in a suit where the court decides to rule because no facts are contested. The big issue was whether what happened constituted physical loss or damage as defined by the builders all-risk policy.
Project Origins
The project began with the state’s plan to create a two-tiered tunnel to replace the Alaska Way Viaduct.
After winning the project contract in 2011, STP obtained a builders’ all-risk policy covering damage to the tunnel and the boring machine. Both STP and the state department of transportation were the beneficiaries.
After the damage, the TBM had to be removed and repaired.Ā 
When STP filed its claim, one of the insurers, Great Lakes Reinsurance UK PLC, denied coverage because it claimed the TBM was under-designed and lacked adequate lubrication.
The trial court had ruled that design defects were not covered under the insurers machinery breakdown exclusion and losses due to delays. The policy, the trial court decided, doesn’t cover the loss of use of the TBM if it can’t function.
The nine-judge panel, reviewing that prior decision and many other similar ones, devoted some of its decision to parsing the plain-language meanings of phrases in the insurance policy, partly to determine if damage caused by a poor design or an inherent defect, as opposed to an external cause, is covered. The judges ultimately ruled that it wasn’t.
On the issue of money lost because of the long delay, STP argued it was owed for those losses because they were not specifically excluded.

Lost Use of the TBM
And the Washington Dept. of Transportation argued it was due coverage because of the loss of use of the TBM. But the panel of judges disagreed.
“Any alleged loss of use of the tunneling works must be a result of, or caused by, some physical condition that impacted the tunneling works,” the nine judges wrote in a unanimous opinion. “Here, WSDOT alleges the physical condition is the physical blockage of the TBM within the tunnel and the loss of use is the inability to continue construction.”Ā 
However, the judges ruled, the “physical condition”ā€”the blockageā€”did not cause the loss of useā€”the inability to continue construction. As WSDOT explained, the TBM and tunneling works “inseparably functioned together to construct the tunnel.”
The TBM couldn’t continue construction, the judges ruled, because it “was inoperable and undergoing repairs.”Ā 
Accordingly, the judges wrote, “even if we interpreted ‘direct physical loss or damage’ to include loss of use, no coverage” is triggered “because the alleged loss of use was not caused by a physical condition impacting the insured property.”

ENR Subscribe
Ā 
Ā 
Deputy Editor Richard Korman, who has edited ENR’s Risk Review newsletter since 2012, helps run ENR’s business coverage and business investigations, selects ENR’s commentary and op-ed viewpoint submissions and oversees editorial content on ENR.com. He has been a fellow on drone safety with the McGraw Center for Business Journalism at the Craig Newmark Graduate School of Journalism at CUNY. In 2015 he won the Timothy White Award from American Business Media for investigations of individual surety fraud and workplace bullying. Richard’s freelance writing has appeared in the Seattle Times, the New York Times, Business Week and the websites of The Atlantic and Salon.com. He admires construction projects that finish on time and budget, pay before the earth completes its annual orbit of the sun, record zero fatalities or serious injuries and assign risk to parties who control an activity or willingly finance the risk.

You must have JavaScript enabled to enjoy a limited number of articles over the next 30 days.
Sponsored Content is a special paid section where industry companies provide high quality, objective, non-commercial content around topics of interest to the ENR audience. All Sponsored Content is supplied by the advertising company. Interested in participating in our Sponsored Content section? Contact your local rep.
Industry Jobs

Free Webinar
Ā 
Getting a grip on the data moving through a project takes more than spreadsheets and off-the-shelf project management software. You’ll learn how toĀ effectively build a data-driven culture in your organization, hear tips on embracing a data-driven approach to construction, and learn to build on past project successes to gain a competitive edge in the future.
Sponsored by:

Itā€™s common to see multiple point solutions or multiple environments of a single program management information system being used to manage projects within a program. But this leads to data silos, making it difficult to keep everyone on the same page. Experts will shareĀ how theyā€™re successfully managing complex programs within a single platform. Ā 
Sponsored by:

Special Ad Section
ENR Green Projects & Products Today
Ā ENR GREEN PROJECTS & PROJECTS TODAY
Ā View all Special Ad Sections
Ā Archives
Ā 
Copyright ©2022. All Rights Reserved BNP Media.
Design, CMS, Hosting & Web Development :: ePublishing

source

About Author